Maintenance of Busbars and Circuit Breakers (Tier III) from 2026-10-19 12:00 CEST to 2026-10-23 19:00 CEST

Maintenance General
2026-10-19 12:00 CEST · 4 days, 7 hours

Updates

Resolved

This maintenance has been concluded as planned.

October 23, 2026 · 19:00 CEST
Started

This maintenance is now starting as planned.

October 19, 2026 · 12:00 CEST
Scheduled

From October 19 to October 23, mandatory inspection and maintenance of the busbars in the server/storage area (2nd floor, TIER III) at the Burckhardtweg 4 (RZGö) location will take place. The redundant power supplies will be shut down one after another (!) to allow the necessary work to be carried out. Devices with a redundant connection to the power grid will remain operational. Devices with a single power supply will temporarily have their power cut off.

October 6, 2026 · 15:38 CEST